工程概况
西乌金山电厂供水工程位于锡林郭勒盟西乌旗境内,主要任务是利用巴拉格尔河地表水和矿坑疏干水为西乌金山电厂供水。工程规模为中型,工程等别为Ⅲ等。本工程包括地表水供水系统和疏干水供水系统。地表水供水工程系统包括拦河闸、贮水池、加压泵站和输水管道。疏干水供水工程系统包括一级泵站、前池、后池和输水管。工程实施后,每年可向供水对象供水176.16万m3。本工程施工总工期为8个月,施工总工时90.67万工时,施工高峰人数589人。
资金筹措情况:工程建设所需资金为西乌金山集团资本金和银行贷款。根据贷款能力测算成果,工程建设资金中,贷款比例为28.52%,资本金4554.09万元,贷款金额1817.26万元,建设期贷款利息65.42万元。

Project Overview
Sioux power plant water supply project is located in Jinshan Xilinguole flag Sioux territory, the main task is to use Balaguer River surface water and mine dewatering water supply plant for the Sioux Jinshan. For medium-scale projects, engineering, etc., etc. Do not for Ⅲ. The works include the supply of surface water drainage systems and water supply system. Surface water system, water supply projects, including gate, storage tank, pumping station and pipeline compression. Dewatering system, water supply projects, including a pumping station, the former pool, after the pool and water pipes. Project, the annual water supply to the water supply targets of 1,761,600 m3. The total construction period of 8 months, construction of 906,700 hours of total working hours, the peak number of construction 589.
Financing: the funds needed for construction projects Sioux Jinshan Group capital and bank loans. Capacity measured in accordance with the results of loans,